# PowerToys Development Guidelines
|
||
|
|
||
|
## Using Open Source Packages and Libraries
|
||
|
|
||
|
### License Considerations
|
||
|
- MIT license is generally acceptable for inclusion in the project
|
||
|
- For any license other than MIT, double check with the PM team
|
||
|
- All external packages or projects must be mentioned in the `notice.md` file
|
||
|
- Even if a license permits free use, it's better to verify with the team
|
||
|
|
||
|
### Safety and Quality Considerations
|
||
|
- Ensure the code being included is safe to use
|
||
|
- Avoid repositories or packages that are not widely used
|
||
|
- Check for packages with significant downloads/usage and good ratings
|
||
|
- Important because our pipeline signs external DLLs with Microsoft certificate
|
||
|
- Unsafe code signed with Microsoft certificate can cause serious issues
|
||
|
|
||
|
## Code Signing
|
||
|
|
||
|
### Signing JSON File
|
||
|
- Modifications to the signing JSON file are typically done manually
|
||
|
- When adding new DLLs (internal PowerToys modules or external libraries)
|
||
|
- When the release pipeline fails with a list of unsigned DLLs/executables:
|
||
|
- For PowerToys DLLs, manually add them to the list
|
||
|
- For external DLLs, verify they're safe to sign before including
|
||
|
|
||
|
### File Signing Requirements
|
||
|
- All DLLs and executables must be signed
|
||
|
- New files need to be added to the signing configuration
|
||
|
- CI checks if all files are signed
|
||
|
- Even Microsoft-sourced dependencies are signed if they aren't already
|
||
|
|
||
|
## Performance Measurement
|
||
|
|
||
|
- Currently no built-in timers to measure PowerToys startup time
|
||
|
- Startup measurement could be added in the runner:
|
||
|
- At the start of the main method
|
||
|
- After all module interface DLLs are loaded
|
||
|
- Alternative: use profilers or Visual Studio profiler
|
||
|
- Startup currently takes some time due to:
|
||
|
- Approximately 20 module interface DLLs that need to be loaded
|
||
|
- Modules that are started during loading
|
||
|
- No dashboards or dedicated tools for performance measurement
|
||
|
- Uses System.Diagnostics.Stopwatch in code
|
||
|
- Performance data is logged to default PowerToys logs
|
||
|
- Can search logs for stopwatch-related messages to diagnose performance issues
|
||
|
- Some telemetry events contain performance information
|
||
|
|
||
|
## Dependency Management
|
||
|
|
||
|
### WinRT SDK and CS/WinRT
|
||
|
- Updates to WinRT SDK and CS/WinRT are done periodically
|
||
|
- WinRT SDK often requires higher versions of CS/WinRT or vice versa
|
||
|
- Check for new versions in NuGet.org or Visual Studio's NuGet Package Explorer
|
||
|
- Prefer stable versions over preview versions
|
||
|
- Best practice: Update early in the release cycle to catch potential regressions
|
||
|
|
||
|
### WebView2
|
||
|
- Used for components like monotone file preview
|
||
|
- WebView2 version is related to the WebView runtime in Windows
|
||
|
- Previous issues with Windows Update installing new WebView runtime versions
|
||
|
- WebView team now includes PowerToys testing in their release cycle
|
||
|
- When updating WebView2:
|
||
|
- Update the version
|
||
|
- Open a PR
|
||
|
- Perform sanity checks on components that use WebView2
|
||
|
|
||
|
### General Dependency Update Process
|
||
|
- When updating via Visual Studio, it will automatically update dependencies
|
||
|
- After updates, perform:
|
||
|
- Clean build
|
||
|
- Sanity check that all modules still work
|
||
|
- Open PR with changes
|
||
|
|
||
|
## Testing Requirements
|
||
|
|
||
|
### Multiple Computers
|
||
|
- **Mouse Without Borders**: Requires multiple physical computers for proper testing
|
||
|
- Testing with VMs is not recommended as it may cause confusion between host and guest mouse input
|
||
|
- At least 2 computers are needed, sometimes testing with 3 is done
|
||
|
- Testing is usually assigned to team members known to have multiple computers
|
||
|
|
||
|
### Multiple Monitors
|
||
|
- Some utilities require multiple monitors for testing
|
||
|
- At least 2 monitors are recommended
|
||
|
- One monitor should be able to use different DPI settings
|
||
|
|
||
|
### Fuzzing Testing
|
||
|
- Security team requires fuzzing testing for modules that handle file I/O or user input
|
||
|
- Helps identify vulnerabilities and bugs by feeding random, invalid, or unexpected data
|
||
|
- PowerToys integrates with Microsoft's OneFuzz service for automated testing
|
||
|
- Both .NET (C#) and C++ modules have different fuzzing implementation approaches
|
||
|
- New modules handling file I/O or user input should implement fuzzing tests
|
||
|
- For detailed setup instructions, see [Fuzzing Testing in PowerToys](../tools/fuzzingtesting.md)
|
||
|
|
||
|
### Testing Process
|
||
|
- For reporting bugs during the release candidate testing:
|
||
|
1. Discuss in team chat
|
||
|
2. Determine if it's a regression (check if bug exists in previous version)
|
||
|
3. Check if an issue is already open
|
||
|
4. Open a new issue if needed
|
||
|
5. Decide on criticality for the release (if regression)
|
||
|
|
||
|
### Release Testing
|
||
|
- Team follows a release checklist
|
||
|
- Includes testing for WinGet configuration
|
||
|
- Sign-off process:
|
||
|
- Teams sign off on modules independently
|
||
|
- Regressions found in first release candidates lead to PRs
|
||
|
- Second release candidate verified fixes
|
||
|
- Command Palette needs separate sign-off
|
||
|
- Final verification ensures modules don't crash with Command Palette integration
|
||
|
|
||
|
## PR Management and Release Process
|
||
|
|
||
|
### PR Review Process
|
||
|
- PM team typically tags PRs with "need review"
|
||
|
- Small fixes from community that don't change much are usually accepted
|
||
|
- PM team adds tags like "need review" to highlight PRs
|
||
|
- PMs set priorities (sometimes using "info.90" tags)
|
||
|
- PMs decide which PRs to prioritize
|
||
|
- Team members can help get PRs merged when there's flexibility
|
||
|
|
||
|
### PR Approval Requirements
|
||
|
- PRs need approval from code owners before merging
|
||
|
- New team members can approve PRs but final approval comes from code owners
|
||
|
|
||
|
### PR Priority Handling
|
||
|
- Old PRs sometimes "slip through the cracks" if not high priority
|
||
|
- PMs tag important PRs with "priority one" to indicate they should be included in release
|
||
|
- Draft PRs are generally not prioritized
|
||
|
|
||
|
### Specific PR Types
|
||
|
- CI-related PRs need review and code owner approval
|
||
|
- Feature additions (like GPO support) need PM decision on whether the feature is wanted
|
||
|
- Bug fixes related to Watson errors sometimes don't have corresponding issue links
|
||
|
- Command Palette is considered high priority for the upcoming release
|
||
|
|
||
|
## Project Management Notes
|
||
|
|
||
|
- Be careful about not merging incomplete features into main
|
||
|
- Feature branches should be used for work in progress
|
||
|
- PRs touching installer files should be carefully reviewed
|
||
|
- Incomplete features should not be merged into main
|
||
|
- Use feature branches (feature/name-of-feature) for work-in-progress features
|
||
|
- Only merge to main when complete or behind experimentation flags
|